Scheduling the operations of a double-load crane in slab yards

This paper studies a double-load crane scheduling problem (DLCSP) in steel slab yards. A slab yard stores slabs in stacks. To prepare for use in production, some slabs need to be moved from one place to another. These movement tasks are performed by a double-load crane which can hold up to two slabs...